GOVERNMENTAL PROJECTS

Finance Department Lobby Remodel for the City of Modesto
March to present, 2005
2,100 sf tenant improvement
$165,000.00 estimated construction costs
Donald W. Phillips AIA, Principal-in-Charge

USPS Remote Encoding Center for Stanislaus County
February 21 to April 27, 1995
 ( Reduced D.D. and C.D. Phases from 45 days to 22 days )
26,101 sf single story steel structure
$789,000.00
Donald W. Phillips AIA, Principal-in-Charge

Sheriff's Operational Center
January 1995 to March 10, 1996 
( Reduced D.D. and C.D. Phases from 120 days to 78 days)
43,000 sf, 2 story structure
$4,679,000.00
Donald W. Phillips AIA, Principal-in-Charge

Riverbank Police Headquarters
March 1993 to December 1994
9,000 sf, planned for 2 story 18,000 sf
$980,000.00
Donald W. Phillips AIA, Principal-in-Charge & Project Architect

Empire Healthy Start, Sheriff’s Office, Medical Center and Library for Stanislaus County
November 1996 to May 1997
6,480 sf relocatable buildings
$554,000.00
Donald W. Phillips AIA, Principal-in-Charge & Project Architect

Imperial Irrigation District Water Control Center
June 1990 to January 1992
10,000 sf Computer Control Center
$1,380,000.00
Donald W. Phillips AIA, Principal-in-Charge & Project Architect

Stanislaus County Courts Remodel
December 1989 to September 1991
18,000 sf of renovation of County Courts Spaces
$1,265,000.00
Donald W. Phillips AIA, Principal-in-Charge & Project Architect
  

Stanislaus County Agricultural Center
March 1996 to 1998
97,256 sf of multiple buildings with conference center, offices, commercial kitchens, laboratories
Donald W. Phillips AIA, Principal-in-Charge
Click here to view Agricultural Center Details Page

Modesto Centre Plaza Parking Structure
1986 to 1987
587 parking spaces, 4 levels
$6,400,000.00
Donald W. Phillips AIA, Principal-in-Charge

Tenth Street Place - Joint Powers Authority
Offices for City of Modesto and
County of Stanislaus
February 1997 to January 1998
220,000 sf  seven floors space planning
$5,500,000.00
Space Planning Consultant to McLarand - Vasquez & Partners
Donald W. Phillips AIA, Principal-in-Charge

Amtrak Station for the City of Modesto
February 1996 to 1999
2,400 sf with 2,400 sf of portico on four acres of site
$2,400,000.00
Donald W. Phillips AIA, Principal-in-Charge

John Thurman Field Renovation
for the City of Modesto
November 1996 to April 1997
Seating for 4,000, new clubhouses, offices, concession stands
$3,900,000.00
Consultants to L.D. Astorino, Ltd.
Donald W. Phillips AIA, Principal-in-Charge

John Thurman Field Press Box
for the City of Modesto
September 1997 to June 1998
Press box for announcers and news media
Two VIP suites for 24 fans
$285,100.00
Donald W. Phillips AIA, Principal-in-Charge

Clubhouse and Maintenance Buildings at
Creekside Golf Course for the City of Modesto
1989
4,800 sf clubhouse, 4,000 sf cart storage barn, 4,000 sf maintenance building
$571,164.00
Donald W. Phillips AIA, Principal-in-Charge & Project Architect

Senior Citizens’ Center for the City of Manteca
February 1987 to May 1988
10,000 sf single story with multi purpose areas
$881,168.00
Donald W. Phillips AIA, Principal-in-Charge

Fire Station #242 for the City of Manteca
January 2000 to May 2002
9,235 sf single story with public use areas
$1,302,734.00
Donald W. Phillips AIA, Principal-in-Charge
Click here to view Fire Station Details Page